Figure 33.1Burgess Pool at a glance

What is here

  • Main pool with diving blocks and bleachers
  • Warm-water instructional pool, covered in season
  • Wading pool
  • Lobby and locker rooms

The 2019 plan's recommendations

Done 0Partly done 0Under way 1Ongoing practice 1Not started 0Not yet published 2

Service requests per year

0
8
11
29
41
1
0

90 since Nov. 2020; 0 open. Median 13 days to close. City record · computed: City's public Cartegraph service-request feed (Nov. 16, 2026)

Lead capital project

CPB023 On hold

Burgess Pool lobby, locker rooms and restrooms · $879,641 City record: Staff Report 26-053-CC: capital program status, FY 2025-26 (April 14, 2026), L-2.6

PoolDistrict 3501 Laurel St.· City of Menlo Park

Pool at Burgess Park, built in 1943 and renovated in 2005, with a warm-water instructional pool covered in season.

A proposal from Councilmember-elect Wonman Lee, not a City document. · 2019 plan, p. 166

Capital projects

CPB023On holdBurgess Pool lobby, locker rooms and restrooms

$879,641 (FY 2025-26) City record: Staff Report 26-053-CC: capital program status, FY 2025-26 (April 14, 2026), L-2.6 · Next: Not yet published

CPP001OngoingAquatic center maintenance

$1,007,799 (FY 2025-26) City record: Staff Report 26-053-CC: capital program status, FY 2025-26 (April 14, 2026), L-2.9 · Next: Not yet published

Measures

2019 recommendations with a known status

A1

Target: Every row placed once staff share their records Proposed

Owner: Library and Community Services · Updated: Quarterly

Plan registerCartegraphHow measured

Service requests in the last 12 months

A3

Target: not yet proposed

Owner: Public Works · Updated: Quarterly

CartegraphHow measured
Figure 33.2Service requests since November 2020, by kind (90 in all)
Pool55
Buildings27
Lights and power5
Restrooms1
Other1
Park and playground repairs1

City record · computed: City's public Cartegraph service-request feed (Nov. 16, 2026) How counted · Buildings: recent counts may be low.

The 2019 plan’s recommendations

  • R022 Under way Study a permanent retractable dome p. 124 · record
  • R023 Not yet published Turn the wading pool into a splash pad or beach entry p. 124
  • R024 Not yet published More shade, cabanas and permanent storage p. 124
  • R025 Ongoing practice Keep maintaining and upgrading the pool's amenities p. 124 · record

Why each status: Appendix A

Pictures

Not yet published

  • Building condition and deferred repairs (a Facility Condition Index), not yet published.
  • Room bookings and hours open, by month, not yet published for this building.
  • The aquatics operator's yearly program hours and swimmers, as a table.

Nearby and related

Last reviewed Nov. 16, 2026. Edition v2026.0. How this is updated (Appendix C)

Sources (3)