Chapter 9 · Part I · The plan
Proposed schedule

Proposed dates: Council direction in January 2027, adoption in December 2027, quarterly updates from February 2028.
- Nov. 2026 Now Commission
Staff present master plan updates to the Commission (Nov. 18)
- Dec. 2026 Work
Scope, staff hours and the first data requests agreed with staff
- Jan. 2027 Council
Council direction on a staff-led update, with staff hours stated
- Jan. 2027 Commission
Commission scopes the work and forms two subcommittees with end dates (Jan. 27)
- Feb. 2027 Quarterly review
First quarterly scorecard; the 2019 register checked by staff (Feb. 24)
- March 2027 Work
Inventory and condition walks; the data book (Mar. 24)
- April 2027 Work
Community input, round 1: online, at events, and in Spanish in Belle Haven
- May 2027 Quarterly review
Second quarterly scorecard; input coded and survey results
- June 2027 Commission
Needs findings (June 23)
- July 2027 Commission
Goals and KPIs, each with a baseline, a target and a date (July 28)
- Aug. 2027 Commission
Projects and priorities, with cost ranges from City bids; annual report to Council
- Sept. 2027 Work
Draft plan published online for 30 days of comment
- Oct. 2027 Council
Council study session; Commission recommendation (Oct. 27)
- Dec. 2027 Council
Council adopts the plan, v2027.1; the tracker goes live
- Feb. 2028 Quarterly review
First quarterly update of the adopted plan