Chapter 11 · Producing the plan: 2019 cost and 2026 estimate

Chapter 11 · Part I · The plan

Producing the plan: 2019 cost and 2026 estimate

Lidar relief of Kelly Park: trees in green, darker where taller; buildings in blue-gray.
Tree canopy at Kelly Park from 2020 lidar: the darker the green, the taller the tree.USGS 3DEP lidar 2020 · City GIS · Public domain (USGS) · City of Menlo Park GIS
Figure 11.1Hours: 2019 consultant (contract schedule) and 2026 staff and volunteers (estimate)
Paid hours (consultant in 2019; City staff in 2026)Volunteer hours
2019: consultant1,168
2026: City staff and volunteers (estimate)1,000 + 408

City record · computed: Staff Report 17-253-CC: the 2019 plan's consultant agreement (Oct. 17, 2017) Estimate

2019: the consultant’s contracts and hours. 2026: this plan’s estimate for City staff and volunteers.

Figure 11.2Outside costs: 2019 consultant contracts and 2026 estimate
2019: consultant contracts$199,710
2026: outside costs, a range (estimate)$0 to $39,925

Hatched: an estimated range, from $0 (without the optional survey and cost check) to $39,925 (both, at their high ends)

City record · computed: Staff Report 19-100-CC: second amendment to the plan agreement (May 14, 2019) Estimate

Figure 11.3Estimated hours by part of the plan
Staff hoursVolunteer hours
1. Setup and management160 + 0
2. Population and growth24 + 16
3. Inventory and condition140 + 60
4. Use and programs24 + 0
5. Access and level of service24 + 8
6. Comparison with other cities24 + 24
7. Community input and needs survey220 + 100
8. Goals and standards40 + 60
9. Recommendations and priorities60 + 60
10. Costs and funding60 + 20
11. Writing it, and this website160 + 60
12. Review and adoption64 + 0
Table 11.1The twelve parts: 2019 fee and 2026 estimate (how each is done: Appendix B)
#Part2019 feeStaff hVolunteer hOutside $
11. Setup and management2019 fee$24,165Staff h160Volunteer h0Outside $$0
22. Population and growth2019 fee$3,900Staff h24Volunteer h16Outside $$0
33. Inventory and condition2019 fee$21,460 (with item 6)Staff h140Volunteer h60Outside $$0
44. Use and programs2019 feeInside item 3Staff h24Volunteer h0Outside $$0
55. Access and level of service2019 feePartly in items 3 and 8Staff h24Volunteer h8Outside $$0
66. Comparison with other cities2019 feeInside item 3Staff h24Volunteer h24Outside $Access terms to check
77. Community input and needs survey2019 fee$39,070, plus $21,195 and $6,700 in amendmentsStaff h220Volunteer h100Outside $$0 to $31,125
88. Goals and standards2019 fee$8,460Staff h40Volunteer h60Outside $$0
99. Recommendations and priorities2019 fee$18,740Staff h60Volunteer h60Outside $$0
1010. Costs and funding2019 fee$27,100Staff h60Volunteer h20Outside $$4,800 to $8,800, optional
1111. Writing it, and this website2019 fee$17,560Staff h160Volunteer h60Outside $$0
1212. Review and adoption2019 feeInside items 10 and 11Staff h64Volunteer h0Outside $$0

The estimate covers producing the plan. Design, construction cost estimates, and legal and environmental review of individual projects are outside it.