Appendix C
Editions and change log

Each edition, what changed and when, and who approves each kind of change.
Editions
v2026.0
First edition. No changes yet: each later edition will be listed here.
Three kinds of change
v2027.1.3
Data refresh: new KPI values and project status, every quarter
Staff update it; no vote needed; the change is logged here.
v2027.2
Minor version: a project added, re-ranked or re-scheduled
The Commission recommends; the Council approves in the budget or capital plan. Every schedule change records its reason: funding, staffing, coordination, scope, another agency, or Council direction.
v2031
Major version: goals or targets change
The Commission recommends; the Council adopts. About every four years, the cadence the Commission's calendar already notes.
Every quarter
- Staff export the numbers from the systems that hold them: Cartegraph (assets, work orders, requests), PerfectMind (bookings, registrations), OpenGov (budget and spending) and the City’s map system.
- A script re-pulls what is already public (park outlines and service requests) and stamps the date.
- Measures, project status and next milestones are updated; every schedule change gets its reason.
- The Parks and Recreation Commission reviews the scorecard in public, and this log records the new edition and its PDF.