Chapter 8 · Capital project and recommendation status

Chapter 8 · Part I · The plan

Capital project and recommendation status

The same aerial view of Willow Oaks Park in 2018 and 2024, side by side.
Then and now: Willow Oaks Park in 2018, and its rebuild nearly done in May 2024.USDA NAIP 2018, 2024 · Public domain (USDA)
Figure 8.1Parks capital projects by budget and status, FY 2025-26
On holdOngoing, planning or design
CPP001 Aquatic center maintenance · Ongoing$1,007,799
CPP002 Bedwell Bayfront Park landfill gas and leachate systems · Design$2,542,697
CPP003 Bedwell Bayfront Park entrance improvements · Design$1,234,790
CPP005 Park improvements (minor) · Ongoing$232,745
CPP006 Park pathways repair · Ongoing$735,080
CPP007 Park playground equipment · Planning$700,955
CPP009 Sport field renovations · On hold$478,571
CPP010 Sport court maintenance · On hold$393,419
CPP020 Kelly Park turf and track replacement · On hold$2,003,177
CPP021 Belle Haven park improvements · On hold$1,300,000

City record: Staff Report 26-053-CC: capital program status, FY 2025-26 (April 14, 2026)

Parks capital budgets and status in the City’s words, and the 2019 recommendations by status. City record: Staff Report 26-053-CC: capital program status, FY 2025-26 (April 14, 2026), L-2.2

Figure 8.2The 2019 plan’s 122 recommendations, by status today
Done 12Partly done 1Under way 17Ongoing practice 12Not started 7Not yet published 73

This plan's analysis: The 2019 plan's recommendations as a register made for this plan, each status with its City record (Nov. 15, 2026)

Figure 8.3The 14 top-priority (Tier 1) projects not funded or started: October 2020 and April 2025
Not funded or startedDone, partly done or under way
October 20208 of 14
April 20255 of 14

City record: Parks and Recreation Commission packet, Oct. 28, 2020: update on the 14 Tier 1 projects (Oct. 28, 2020) City record: City page for the master plan, with its Tier 1 status table (updated April 29, 2025)

The measures

Parks capital dollars on hold

6.1

Target: not yet proposed

Owner: Public Works, with Finance · Updated: Quarterly

Capital program reportOpenGovHow measured

2019 recommendations placed by status from public records

6.2

Target: 110 or more of 122, with staff data, by October 2027 Proposed

Owner: Library and Community Services, with a Commission subcommittee · Updated: Quarterly

Plan registerCartegraphCapital program reportHow measured